✨ Construction Progress Update | Kandoofaa Residence
Our project continues to progress steadily, with significant advancements across Levels 2–12. We are pleased to share the latest construction updates:
🏗 Key Structural & External Works
Balcony sliding doors, window frames, and glass installation — 90% completed
External wall plastering — 100% completed
External wall putty — 80% completed
Staircase finishing works — 100% completed
🏠 Interior Works Progress
Internal wall plastering — 100% completed
Indoor putty works — 50% completed
Wall and floor tiling — 70% completed
Ceiling works — 60% completed
⚙️ MEP Works
Drainage and water supply systems — 100% completed
Electrical works — 90% completed
HVAC installation — 80% completed
✨
Each milestone brings us closer to delivering a high-quality, modern living environment for our future residents. We remain committed to maintaining construction quality and progress as scheduled.